文章摘要
姜 楠, 刘永强.基于BIM与VB技术的水闸模型信息应用Journal of Water Resources and Water Engineering[J].,2018,29(6):145-150
基于BIM与VB技术的水闸模型信息应用
Application of sluice model information based on BIM and VB
  
DOI:10.11705/j.issn.1672-643X.2018.06.22
中文关键词: 三维建模  二次开发  BIM  VB编程  施工控制  信息追踪  施工管理
英文关键词: 3D modeling  secondary development  BIM(Building Information Modeling)  VB programming  construction control  message tracking    construction management
基金项目:江苏高校优势学科建设工程项目
Author NameAffiliation
JIANG Nan, LIU Yongqiang (河海大学 水利水电学院 江苏 南京 210098) 
Hits: 1522
Download times: 873
中文摘要:
      针对三维模型应用与实际工程施工之间存在脱节问题,为解决模型信息提取繁琐、施工工程变更不易修改、操作工序复杂等不足,以实现三维模型信息更好地服务于水利工程施工为目标,采用BIM与VB技术,以实际水闸工程为例,对水闸进行族参数建模,动态提取需要的施工图纸并通过二次开发对模型的工程量进行提取并编制工程概算。其次,利用VB技术编程,设计建立施工资源配置窗口,以上述工程概算中的数据为基础,完成施工进度图和人材机计划表的动态生成。最后,形成建模、图纸、概算、施工进度及人材机计划五位一体的模型信息应用系统,从模型信息的提取、处理至共享,实现三维模型信息的动态关联和追踪,对水闸三维建模与模型信息在施工中的应用进行了初步探索。研究表明:BIM与VB技术相结合对有效提高水利工程施工进度管理和进一步提升水利工程施工效率均有较好的适用性和实用性。
英文摘要:
      Aiming to solve the disconnect problems between 3D modeling and the construction of the actual engineering, such as the difficulty of the extraction of model's information, the difficulty to modify the changes of the engineering and the complexity of the process of construction, this paper chose the technology of BIM and VB to make the information of 3D modeling better serve the construction. First, according to an actual sluice project, we extract the needed construction drawings and make the project budget through the secondary development of Revit after building the model's family parameters of the sluice. At the same time, we use VB technology to design the window for the configuration of the construction's resources to exert the chart of the construction's process dynamically on the base of the data from the budget we made before. Finally, we can build an application system that modeling, drawings, budget, construction process and the plan of manual work, materials and machinery will be included, in which we can make a preliminary exploration on how to use the information of 3D modeling in the construction of the sluice project, from the collection, management to the share of the information to realize the dynamic correlation of 3D modeling. According to the research, the combination of VB and BIM will effectively improve the management of the construction schedule and further improve its efficiency, which has a great applicability and practicability.
View Full Text   View/Add Comment  Download reader
Close
function PdfOpen(url){ var win="toolbar=no,location=no,directories=no,status=yes,menubar=yes,scrollbars=yes,resizable=yes"; window.open(url,"",win); } function openWin(url,w,h){ var win="toolbar=no,location=no,directories=no,status=no,menubar=no,scrollbars=yes,resizable=no,width=" + w + ",height=" + h; controlWindow=window.open(url,"",win); } &et=DCA5CABA83612A949DB8F12614CC4D3FFFE045EEEC58A0D881C525D86D90BF234C390A928A94CF24D9B30FA55EFA2F17CC203A50D884C5713B5E9CD644D71083&pcid=5B3AB970F71A803DEACDC0559115BFCF0A068CD97DD29835&cid=3ECA06F115476E3F&jid=BC473CEDCB8CE70D7B12BDD8EA00FF44&yid=EA357AD73C8E13BC&aid=0B4BF5AC87809E484C0F6D943968DC86&vid=&iid=B31275AF3241DB2D&sid=769BD58726D66E7D&eid=2DBBF45CC176713E&fileno=20180622&flag=1&is_more=0">